Measure M Construction Update for Week Beginning: 3/25/19

Math/Science Project: Ongoing miscellaneous deliveries involving large trucks entering and exiting the site. Continued exterior finishing, glass installation, and interior drywall, painting, flooring, casework, and ceiling finishing. Continued mechanical, electrical,...

Measure M Construction Update for Week Beginning: 3/18/19

Math/Science Project: Ongoing miscellaneous deliveries involving large trucks entering and exiting the site. Continued exterior finishing, glass installation, and interior drywall, flooring, casework, and ceiling finishing. Continued mechanical, electrical, and...

Measure M Construction Update for Week Beginning: 3/11/19

Math/Science Project: Ongoing miscellaneous deliveries involving large trucks entering and exiting the site. Continued exterior finishing, glass installation, and interior drywall, flooring, casework, and ceiling finishing. Continued mechanical, electrical, and...

Measure M Construction Update for Week Beginning: 3/4/19

Math/Science Project: Ongoing miscellaneous deliveries involving large trucks entering and exiting the site. Continued exterior finishing, glass installation, and interior drywall, flooring, casework, and ceiling finishing. Continued mechanical, electrical, and...

Measure M Construction Update for Week Beginning: 2/25/19

Math/Science Project: Ongoing miscellaneous deliveries involving large trucks entering and exiting the site. Continued scaffolding removal, exterior finishing, glass installation, and interior drywall and ceiling finishing. Continued mechanical, electrical, and...

Measure M Construction Update for Week Beginning: 2/18/19

Math/Science Project: Ongoing miscellaneous deliveries involving large trucks entering and exiting the site. Continued scaffolding removal, exterior finishing, glass installation, and interior drywall and ceiling finishing. Continued mechanical, electrical, and...