Measure M Construction Update for Week Beginning: 5-21-18

Math/Science Project: Ongoing deliveries of structural steel and concrete involving large trucks entering and exiting the site. Ongoing steel bolting, welding, and installation of metal decking. Construction crews will be working on Saturdays until further notice;...

Measure M Construction Update for Week Beginning: 5-14-18

Math/Science Project: Ongoing deliveries of structural steel and concrete involving large trucks entering and exiting the site. Ongoing steel bolting, welding, metal decking, underground trenching, piping, and rebar work at the site. Parking Lot C and the pedestrian...

Measure M Construction Update for Week Beginning: 5-7-18

Math/Science Project: Ongoing deliveries of structural steel involving large trucks entering and exiting the site. Concrete pour for slab on grade metal deck is schedule for Thursday May 10th. Ongoing crane activity, steel bolting, welding, metal decking, underground...

Measure M Construction Update for Week Beginning: 4-30-18

Math/Science Project: Ongoing deliveries of structural steel involving large trucks entering and exiting the site. Ongoing crane activity, steel bolting, welding, metal decking, underground trenching, piping, and rebar work at the site. Construction crews will be...

Measure M Construction Update for Week Beginning: 4-23-18

Math/Science Project: Ongoing deliveries of structural steel involving large trucks entering and exiting the site. Ongoing crane activity, steel bolting, welding, metal decking, underground trenching, piping, and rebar work at the site. Construction crews will be...

Measure M Construction Update for Week Beginning: 4-16-18

Student Services Project: Ongoing miscellaneous furniture installations. Campus student services departments have occupied the building and the services within are now available to the student body. Criminal Justice Project: The Pull Over Lane adjacent to Parking Lot...