Measure M Construction Update: 4-27-17

Measure M Construction Update: Student Services Project:  Monday 5/1 the crane will mobilize and enter the campus through the main construction access road early in the morning.  Concrete pour for roof deck is scheduled Monday 5/1 and Tuesday 5/2.  Delivery of...

Measure M Construction Update: 4-14-17

Measure M Construction Update: Student Services Project:  Concrete pour for 2nd floor deck is scheduled Wednesday 4/19.  Another concrete pour is scheduled Thursday 4/20  for bridge columns.  Delivery of concrete trucks is scheduled with trucks entering thru the main...

Measure M Construction Update: 4-7-17

Measure M Construction Update: Student Services Project:  Concrete pour for north canopy footings is scheduled for Thursday 4/13.  Another concrete pour scheduled for Friday 4/15 for first deck pour.  Delivery of concrete trucks is scheduled for this week with trucks...

Measure M Construction Update: 3-30-17

Measure M Construction Update: Student Services Project:  Concrete pour for north canopy footings is scheduled for Monday 4/3.  Welding for metal deck ongoing with erection of canopy.  Delivery of steel and scaffolding is scheduled for this week with trucks entering...

Asphalt repairs – North Gothard Lot – March 27 – 31

Starting next week, March 27 – March 31, we will be making repairs and sealing the North Gothard parking lot. This will NOT affect the Center drive entrance all work will be North of Center. On Monday and Tuesday the main lot will be closed except for the drive...

Measure M Construction Update: 3-17-17

Measure M Construction Update: Student Services Project:  Weather permitting concrete pour for north canopy footings is scheduled for Thursday 3/23.  Steel deliveries is scheduled for this week with trucks entering thru the main construction access road.  The main...