Measure M Construction Update for week beginning: 8-14-17

Measure M Construction Update: Student Services Project: Start grading site at north end of building. Ongoing lay out of exterior terra cotta. Ongoing of insulating interior and exterior walls. Ongoing installation of exterior windows and flashings around doors and...

Measure M Construction Update: 8-14-17

Measure M Construction Update: Student Services Project:  Start grading site at north end of building.  Ongoing lay out of exterior terra cotta.  Ongoing of insulating interior and exterior walls.  Ongoing installation of exterior windows and flashings around doors...

Measure M Construction Update: 7-31-17

Measure M Construction Update: Student Services Project:  Start installation of exterior terra cotta.  Ongoing of insulating interior and exterior walls.  Ongoing installation of exterior windows.  Ongoing 2nd floor rough end of Mechanical, Electrical, and Plumbing...

Measure M Construction Update: 7-21-17

Measure M Construction Update: Student Services Project:  Start of insulating interior and exterior walls.  Heavy duty crane is scheduled to mobilize Wednesday 7/26 to lift air conditioning rooftop units.  Ongoing installation of exterior windows.  Ongoing 2nd floor...

Measure M Construction Update 7-14-17

Measure M Construction Update7/14/17: Student Services Project:  Ongoing installation of exterior windows.  Ongoing rough end of Mechanical, Electrical, and Plumbing installation.  Ongoing exterior and interior framing.  Continue hanging exterior dens glass.  Ongoing...

Measure M Construction Update: 7-7-17

Measure M Construction Update: Student Services Project:  Start of installation of exterior windows.  Ongoing rough end of Mechanical, Electrical, and Plumbing installation.  Ongoing exterior and interior framing.  Continue hanging exterior dens glass.  Miscellaneous...