Measure M Construction Update for Week Beginning: 4-9-18

Student Services Project: Ongoing miscellaneous furniture installations. Campus student services departments have occupied the building and the services within are now available to the student body. Criminal Justice Project: The Pull Over Lane adjacent to Parking Lot...

Measure M Construction Update for Week Beginning: 4-2-18

Student Services Project: Ongoing miscellaneous furniture installations. Campus student services departments have occupied the building and the services within are now available to the student body. Criminal Justice Project: The Pull Over Lane adjacent to Parking Lot...

Measure M Construction Update for Week Beginning: 3-26-18

Student Services Project: The building remains closed to the public at this time. There will be asphalt re-paving Thursday, Mar. 29 on the road between the Native Garden and Auto Tech, all the way to Cosmetology and Main Street, as well as portions of the access road...

Measure M Construction Update for Week Beginning: 3-19-18

Student Services Project: Ongoing furniture installations inside the building. Relocation of Staff from around campus to the building begins on Friday, Mar. 23. Moving trucks, carts, and movers may cause light congestion on pathways leading to the building; please...

Measure M Construction Update for Week Beginning: 3-12-18

Student Services Project: Ongoing furniture installations inside the building. The building remains closed to the public at this time. Deliveries will be made on the road between the Native Garden and Auto Tech, all the way to Cosmetology and Main Street, which may...

Measure M Construction Update for Week Beginning: 3-5-18

Student Services Project: Ongoing furniture installations inside the building. The building remains closed to the public at this time. Deliveries will be made on the road between the Native Garden and Auto Tech, all the way to Cosmetology and Main Street, which may...