Measure M Construction Update:

Student Services Project:  Ongoing rough end of Mechanical, Electrical, and Plumbing installation.  Ongoing exterior and interior framing.  Delivery of dens glass for exterior and interior is scheduled for Wednesday 5/24 with trucks entering thru the main access road.  The main construction access road is the road between the Native Garden and Auto Tech all the way to Cosmetology.   Miscellaneous material and deliveries is scheduled the week of 5/22 with trucks entering thru the access road between Kaplan and Amphitheater.  Please exercise caution around the construction equipment as they enter the campus and follow directions from the flagmen.  Noise levels will be moderate due to large equipment for these activities.  Summer work schedule will begin May 30th which entails: Pedestrian walkway along Cosmetology and Student Service project site will be temporary closed for placement of new sidewalk.  East stairway to access 2nd floor Music will be closed the duration of summer for removal/replacement of new stairs and sidewalk.  Pavement repair work along access road between Kaplan/Amphitheater and access road between the Bookstore/Humanities is scheduled to ensure path of travel is ADA compliant. See attached GWC map [PDF].

Criminal Justice Project:  Ongoing rough end of Mechanical, Electrical, and Plumbing installation.  Ongoing metal stud framing.  Start of CMU/Block wall erection at parking lot G is scheduled the week of 5/22.  Concrete pour for CMU/Block wall footing is scheduled Tuesday 5/23.  Ongoing deliveries of miscellaneous material scheduled.  Pedestrians and Drivers need to follow closure signs and be cautious as they travel around the construction site.  Noise levels will be moderate due to the large equipment for these activities.  Fencing for the dirt lot adjacent to Parking Lot G has been installed.   The dirt lot will be closed for any public parking until the project is complete.  The access road will remain open for the majority of the construction project with short periods of closure for work on the road.  Phase 1 of trenching outside project site for underground utilities is completed.  Phase2 Trenching outside project site for new underground gas line is scheduled to begin Monday 5/21/17.  See attached Gas Feed work plan.  Weeks of May 8th – July 10th fencing for the dirt lot adjacent to Parking Lot G will be moved and encroach on traffic lane to begin grading for pull over lane.  The access road between parking lots G and H will be closed full time 7 days a week starting Monday 6/5/17 and reopened 7/28/17. See attached GWC map [PDF].

Math/Science Project:  DSA approved building plans were issued on 3/21/17.  Bid date scheduled for 5/25/17.  Notice to proceed to contractors scheduled for 6/22/17.  Please note that the parking lot sidewalk west of the project is closed for the duration of the project.  A temporary pedestrian walkway has been created in the parking lot to accommodate all pedestrian traffic through this area.

Security Project:  Physical installation of cameras, emergency phone, access control antennas, and emergency phone towers are completed.  Ongoing inspections of project scope of work and closeout  turnover.

General Note:  For any additional questions or clarifications, please email Randy Flint atrflint@gwc.cccd.edu.