Student Services Project:  Continued grading of site for concrete.  Ongoing installation of exterior terra cotta.  Ongoing insulating of interior and exterior walls.  Ongoing installation of exterior windows, trim and lath.  Ongoing 2nd floor rough end of Mechanical, Electrical, and Plumbing installation.  Ongoing interior installation of drywall.  Ongoing installation of roof and elevator.  Prepare to re-open stairway at music building. Sidewalk along Cosmetology building is now open to the public.  Miscellaneous deliveries will be made on the main construction access road, which may cause congestion.  The main construction access road is the road between the Native Garden and Auto Tech all the way to Cosmetology.   Please exercise caution around the construction equipment as they enter the campus, and follow directions from the flagmen.  Noise levels will be moderate due to large equipment for these activities.  Summer work schedule began May 30th which entails: Pedestrian walkway along Cosmetology and Student Service project site– completed.  West stairway on Music Bldg to access 2nd floor- anticipated completion by end of the week.  Pavement repair workcontinues along access road between Kaplan/Amphitheater to ensure path of travel is ADA compliant (See attached GWC Map).

Criminal Justice Project:   Footings for the Scenario Lab are scheduled to be poured 8/22/17. Ongoing exterior stucco operation.  Ongoing installation of interior drywall.  Ongoing site utility connections.  Ongoing rough end of 2nd floor Mechanical, Electrical, and Plumbing installation.  Ongoing installation of underground utilities at Scenario Lab.  Ongoing deliveries of miscellaneous material scheduled.  Curbs, sidewalk, and paving at south access road have been completed, and the south access road will be ready for use early in the week, with intermittent closures for construction activity.  Pedestrians and Drivers need to follow closure signs and be cautious as they travel around the construction site.  Noise levels will be moderate due to the large equipment for these activities.  Fencing for the dirt lot adjacent to Parking Lot G has been installed.   The dirt lot will be closed for any public parking until the project is complete.   Parking Lot H and Parking Lot I are open for vehicle parking; watch for deliveries.  The drive isle near Kaplan will remain closed this week to install underground water main; paving is scheduled by the end of the week (See attached GWC Map for site impact).  The access road between Theater and Criminal Justice project site will remain closed this week for underground utility connections and site hardscape work for ADA walkway improvement (See attached GWC Map for site impact, walkway closures, traffic lane closures and pedestrian access).  The south access road between parking lots G and H will be re-opened early in the week, but will be closed intermittently due to construction activity- please exercise caution and drive slowly on the access road as it is narrow and difficult to see oncoming traffic.  Beginning 8/7/17, the traffic lane along the dirt lot in Parking Lot G will be closed periodically for truck deliveries / traffic into the dirt lot area for pavement of the pull over lane, and construction vehicles en route to the Scenario Lab  (See attached GWC Map).

Math/Science Project:  Ongoing pile drilling, reinforcement, and concrete placementoperations consisting of large equipment, including Drilling Rigs.   Noise level expected to be moderate due to large equipment for these activities.  Please be cautious of construction traffic and follow safety directions from workers directing traffic.  Please note that the parking lot sidewalk west of the project is closed for the duration of the project.  A temporary pedestrian walkway has been created in the parking lot to accommodate all pedestrian traffic through this area.

General Note:  For any additional questions or clarifications, please email Randy Flint at rflint@gwc.cccd.edu.