Student Services Project: Ongoing miscellaneous furniture installations. Campus student services departments have occupied the building and the services within are now available to the student body.

Criminal Justice Project: The Pull Over Lane adjacent to Parking Lot G remains closed to the public at this time. Please exercise caution and drive slowly on the south access road between Parking Lots G and H as it is narrow and difficult to see oncoming traffic.

Math/Science Project: Ongoing deliveries of structural steel involving large trucks entering and exiting the site. Ongoing crane activity, steel bolting, welding, underground trenching, piping, and rebar work at the site. Construction crews will be working on Saturdays until further notice; there will be no impact on the Swap Meet. Sections of Parking Lot C may be blocked off for these activities; if so, pathways near the area will be delineated. Please obey delineations, be cautious of construction traffic, and follow safety directions from workers directing traffic. Noise level expected to be moderate due to large equipment for these activities. The sidewalk west of the project is closed for the duration of the project. A temporary pedestrian walkway has been created in Parking Lots C and D to accommodate all pedestrian traffic through this area. (See attached GWC map [PDF] for pedestrian walkway and Construction Vehicle Routes)

General Note: For any additional questions or clarifications, please email Randy Flint at rflint@gwc.cccd.edu.