Student Services Project: Ongoing planting around the site. Preparations for planting sod along the front/south side of the building will commence, including relocation of the chain link fence, and installation of a temporary fence between the new sod and existing grass in the quad. Continued exterior painting. Ongoing testing and troubleshooting of systems throughout. Miscellaneous deliveries will be made on the access road between Kaplan and the Amphitheater, and the on road between the Native Garden and Auto Tech all the way to Cosmetology and Main Street, which may cause congestion. Please exercise caution around the construction equipment as they enter the campus, and follow directions from the flagmen. Noise levels will be moderate due to large equipment for these activities. (See attached GWC map [PDF] for Construction Vehicle Routes).

Criminal Justice Project: Construction work for a new drop off area and walkways will commence on the ‘meadow’ north of the building site beginning Jan.8. Parking Lot I and the adjacent sidewalk will be closed from Jan. 8 through Jan. 19, 2018. Please see the attached map for affected areas. Ongoing construction activity at the Scenario Lab. The Pull Over Lane remains closed for public parking until further notice. Pedestrians and Drivers need to exercise caution as they travel around the construction site. Noise levels will be moderate due to the large equipment for these activities. The south access road between Parking Lots G and H may be closed intermittently due to construction activity- please exercise caution and drive slowly on the access road as it is narrow and difficult to see oncoming traffic. The traffic lane along the fenced Pull Over Lane in Parking Lot G may be closed periodically for construction vehicles en route to the Scenario Lab. (See attached GWC map [PDF] for areas subject to periodic closure, and Construction Vehicle Routes).

Math/Science Project: Continued underground trenching for pipe installation. Ongoing site grading and placing of concrete involving large equipment and concrete trucks entering and exiting the site. Noise level expected to be moderate due to large equipment for these activities. Please be cautious of construction traffic and follow safety directions from workers directing traffic. The sidewalk west of the project is closed for the duration of the project. A temporary pedestrian walkway has been created in Parking Lots C and D to accommodate all pedestrian traffic through this area. (See attached GWC map [PDF] for pedestrian walkway and Construction Vehicle Routes).

General Note: For any additional questions or clarifications, please email Randy Flint at rflint@gwc.cccd.edu.