Student Services Project: Ongoing furniture delivery and installation with large trucks staging delivery on Main street. The building remains closed to the public at this time. Deliveries will be made on the road between the Native Garden and Auto Tech, all the way to Cosmetology and Main Street, which may cause congestion. Please exercise caution around the delivery equipment as they enter the campus, and follow directions from the flagmen. Noise levels will be minimum due to these activities. (See attached GWC map [PDF] for Construction Vehicle Routes)

Criminal Justice Project: The north access road between the building site and the Theater will be closed for asphalt re-work from Monday Feb 26 through Wednesday Feb 28. For pedestrian access, please use the new sidewalk in the ‘meadow’ via the new pullover lane in parking lot I, or the sidewalk along the front of the Criminal Justice building. A small portion of parking lot H will be temporarily blocked off for staging of equipment for the asphalt work. Continued construction activity at the Scenario Lab with light construction traffic at the south access road. Pedestrians and Drivers need to exercise caution as they travel around the construction site. The Pull Over Lane adjacent to Parking Lot G remains closed to the public. The south access road between Parking Lots G and H may be closed intermittently due to construction activity- please exercise caution and drive slowly on the access road as it is narrow and difficult to see oncoming traffic. (See attached GWC map [PDF] for areas subject to periodic closure, and Construction Vehicle Routes)

Math/Science Project: Large truck deliveries of structural steel will commence mid-week, and delivery and set up of a large crane in parking lot C is expected by the end of the week. Sections of parking lot C will be blocked off for these activities, and pathways near the area will be delineated. Please obey delineations, be cautious of construction traffic, and follow safety directions from workers directing traffic. Noise level expected to be moderate due to large equipment for these activities. The sidewalk west of the project is closed for the duration of the project. A temporary pedestrian walkway has been created in Parking Lots C and D to accommodate all pedestrian traffic through this area. (See attached GWC map [PDF] for pedestrian walkway and Construction Vehicle Routes)

General Note: For any additional questions or clarifications, please email Randy Flint at rflint@gwc.cccd.edu.