Student Services Project:  Ongoing installation of exterior terra cotta.  Ongoing installation of exterior trim and lath.  Installation of exterior glass and curtain wall system.  Ongoing Mechanical and Electrical installation, including HVAC ducting and overhead for fire alarm.  Ongoing interior taping of drywall.  Ongoing installation of roof and elevator.  Installation of forms at the bridge area, including handrails. Excavation for installation of sleeves for irrigation; installation of catch basins and clean outs.  Miscellaneous deliveries will be made on the main construction access road, which may cause congestion.  The main construction access road is the road between the Native Garden and Auto Tech all the way to Cosmetology.   Please exercise caution around the construction equipment as they enter the campus, and follow directions from the flagmen.  Noise levels will be moderate due to large equipment for these activities.  The Summer work schedule has been completed: Pedestrian walkway along Cosmetology and Student Service project site is open.  West stairway on Music Bldg to access 2nd floor is open.  Access road between Kaplan/Amphitheater is open. (See attached GWC map for Construction Vehicle Routes)

Criminal Justice Project:   Ongoing exterior stucco operation.  Ongoing installation of interior drywall.  Ongoing site utility connections.  Ongoing rough end of 2nd floor Mechanical, Electrical, and Plumbing installation.  Ongoing construction activity at Scenario Lab.  Ongoing miscellaneous deliveries scheduled.  Pedestrians and Drivers need to follow closure signs and be cautious as they travel around the construction site.  Noise levels will be moderate due to the large equipment for these activities.  The dirt lot adjacent to Parking Lot G remains closed for any public parking. Parking Lot H and Parking Lot I are open for vehicle parking; watch for deliveries.  The drive isle near Kaplan has been paved and reopened.  The access road between Theater and Criminal Justice project site has been reopened. The south access road between parking lots G and H has been repaved and a pedestrian sidewalk has been added.  It is now accessible to through traffic, but will be closed intermittently due to construction activity- please exercise caution and drive slowly on the access road as it is narrow and difficult to see oncoming traffic.  The traffic lane along the dirt lot in Parking Lot G will be closed periodically for truck deliveries and traffic into the dirt lot area, and for construction vehicles en route to the Scenario Lab.  (See attached GWC map for areas subject to periodic closure, and Construction Vehicle Routes)

Math/Science Project:  Ongoing pile drilling, reinforcement, and concrete placementoperations consisting of large equipment, including drilling rigs.  Ongoing grading and dirt export from the site.  Noise level expected to be moderate due to large equipment for these activities.  Please be cautious of construction traffic and follow safety directions from workers directing traffic.  Please note that the parking lot sidewalk west of the project is closed for the duration of the project.  A temporary pedestrian walkway has been created in the parking lot to accommodate all pedestrian traffic through this area. (See attached GWC map for pedestrian walkway and Construction Vehicle Routes)

General Note:  For any additional questions or clarifications, please email Randy Flint at rflint@gwc.cccd.edu.