Student Services Project: Ongoing installation of exterior terra cotta, exterior trim and lath, plaster scratch coat, and Curtain Wall. Installation of forms and placing of concrete at the bridge area; this concrete is scheduled to be poured on Thursday, 9/14, with truck delivery via the access road between Kaplan and the Amphitheater; watch for intermittent closures. Ongoing excavation for installation of sleeves for irrigation; installation of catch basins. Ongoing interior taping of drywall and painting. Ongoing placement of overhead electrical; beginning installation of the acoustical grid. Beginning installation of ceramic tile in the restrooms. Miscellaneous deliveries will be made on the main construction access road, which may cause congestion. The main construction access road is the road between the Native Garden and Auto Tech all the way to Cosmetology. Please exercise caution around the construction equipment as they enter the campus, and follow directions from the flagmen. Noise levels will be moderate due to large equipment for these activities. (See attached GWC map for Construction Vehicle Routes)

Criminal Justice Project: Ongoing exterior stucco operation and roofing installation. Interior priming and painting of drywall. Ongoing site utility connections. Ongoing rough end of 2nd floor Mechanical, Electrical, and Plumbing installation. Ongoing construction activity at Scenario Lab. South access road between Parking Lots G and H will be closed intermittently for road striping. Striping will also be done for the ADA pathways in Parking lots H & I, and there will be electrical infrastructure work along the access road between Kaplan and the Amphitheater. Please observe caution tape and closures in these areas. The dirt lot adjacent to Parking Lot G has been paved and will be used as a Pull Over Lane in conjunction with the Scenario Lab. Concrete will be delivered and poured for curb work in the Pull Over Lane with trucks entering Parking Lot G off of Edinger. The Pull Over Lane remains closed for public parking until further notice. Pedestrians and Drivers need to follow closure signs and be cautious as they travel around the construction site. Noise levels will be moderate due to the large equipment for these activities. The south access road between Parking Lots G and H will be closed intermittently due to construction activity- please exercise caution and drive slowly on the access road as it is narrow and difficult to see oncoming traffic. The traffic lane along the fenced Pull Over Lane in Parking Lot G will be closed periodically for truck deliveries and traffic into the Pull Over Lane area, and for construction vehicles en route to the Scenario Lab. (See attached GWC map for areas subject to periodic closure, and Construction Vehicle Routes).

Math/Science Project: Ongoing pile drilling, reinforcement, and concrete placement operations consisting of large equipment, including drilling rigs. Ongoing grading and dirt export from the site. Noise level expected to be moderate due to large equipment for these activities. Please be cautious of construction traffic and follow safety directions from workers directing traffic. The sidewalk west of the project is closed for the duration of the project. A temporary pedestrian walkway has been created in Parking Lots C and D to accommodate all pedestrian traffic through this area. (See attached GWC map for pedestrian walkway and Construction Vehicle Routes).

General Note: For any additional questions or clarifications, please email Randy Flint at rflint@gwc.cccd.edu