Language Arts Complex- Measure M: Construction activity continues in the old CJ area to prepare swing space for necessary relocations due to upcoming demolitions. Beginning Monday, there will be additional construction traffic due to the removal of surplus furniture and the arrival of low voltage contractors. Construction vehicles will enter from parking lot F. Please exercise caution and avoid these areas on campus. The noise level is expected to be moderate due to large equipment for these activities. (See attached map [PDF] for work areas and construction vehicle routes).

Classroom Improvements- Measure M: The summer mod to upgrade AV/IT equipment in select classrooms across campus is underway. Delivery and installation vehicles will be on campus. The noise level is expected to be low for these activities.

Music Restoration Project- Campus: Work has commenced to restore select rooms in the Music bldg., with drywall installation beginning on Monday. Construction vehicles will be entering and exiting campus via Parking lot I and the service road between the Amphitheater and Kaplan. Please exercise caution and avoid these areas on campus. The noise level is expected to be moderate due to large equipment for these activities. (See attached map for work areas and construction vehicle routes).

General Note: For any additional questions or clarifications, please email Mike Golden at mgolden7@gwc.cccd.edu for Measure M projects, Frank Fonseca at ffonseca1@gwc.cccd.edu. for Campus projects.