SKIP TO PAGE CONTENT

Construction Update for Week Beginning: 6/5/23

Language Arts Complex - Measure M:
Construction activity continues on the interior with ceilings, flooring, doors and hardware, and interior storefront framing. Exterior finishing continues with metal panel installation. Site work continues with grading and flatwork in preparation for placing concrete. To accommodate site work, construction fences have been extended on the north-west side at the GenEd bldg, preventing passage from the LRC through Gen Ed to the Bookstore (the entrances to the LRC are unaffected), and on the south side blocking the pathway between the Math & Science bldg and the Business bldg/Forum 1. Adjacent sidewalks and pathways to the south may be used to navigate around this obstacle. Please use the Campus pedestrian entrances to the north between Auto Tech and the Native Garden, and to the south between Math & Science and Public Safety to access the campus from the west parking lots off of Goldenwest St; allow extra time to reach your destination. There may be increased construction traffic due to site work activity; use caution around trucks entering and exiting through Parking lot C. Portions of Parking Lot C remain barricaded for construction traffic; there is no parking within the barricades. Please watch for and obey the flagmen in this area. Roads and walkways within fenced off construction areas are not accessible to pedestrian traffic; please use alternate routes to get around Campus. Exercise caution around construction vehicles and areas surrounding the construction site. Noise level will be low to medium for these activities. (See attached map [PDF] for work areas and construction vehicle routes)

Nursing and Health Services - Campus:
Renovation continues at the Nursing and Health Services building. Please use caution around this area and watch for contractors entering and exiting the building/area. Noise level will be low for these activities. (See attached map [PDF] for work area)

Technology Bldg. Handrail Installation - Campus:
Handrail installation has been completed.

Old Softball/Utility Field Removal - Campus:
Restoration of the area at the corner of McFadden and Gothard on the northeast end of campus (where the old softball/utility field was removed) continues this week. The area is being restored with new soil, irrigation and sod. Please avoid this area and watch for contractors entering and exiting the site. Noise level will be low for these activities. (See attached map [PDF] for work area)

Site Restoration Project - Campus:
Restoration of the demolition site from the old KOCE building is in progress. The site, which is located on the east side of campus between the Amphitheater and Fine Arts, north of Forum 2, will remain fenced off with no public access within the fence. (See attached map [PDF] for work area)

Campus Wi-Fi Project - District:
Wireless Access Points are being upgraded throughout campus. Work continues with installation of outdoor Access Points. Contractors will delineate work areas. Please use caution around construction vehicles and equipment, and avoid those areas.

General Note:
For any additional questions or clarifications, please email Mike Golden at mgolden7@gwc.cccd.edu for Measure M projects, and Frank Fonseca at ffonseca1@gwc.cccd.edu or Joe Dowling at jdowling@gwc.cccd.edu for Campus projects.

curve